Although Phase 1 was completed a week early, they have encountered engineering difficulties on Phase 2 and now expect it to be completed by 21 August. They still expect the whole thing to last the original 6 weeks. There have been a few incidents such as all three of the temporary traffic lights showing red for some time, causing tempers to fray and lots of angry horn tooting. But SGN have responded quickly when we reported this. Below is their latest message. Marie
…………………………………………………………….
Phase One – Croydon Road, junction with Elmers End Road This phase progressed well and was completed a week earlier than planned on Saturday 27 July Phase Two – Croydon Road, between junction of Elmers End Road and Clock House Road Phase Two started on Monday 29 July, a week earlier than originally planned Our engineers moved location to the other side of the Elmers End Road junction from phase one and began working on the next section of Croydon Road We now expect this phase to last approximately three and a half weeks in total To ensure everyone’s safety we have temporarily closed the eastbound lane of Croydon Road across the Elmers End Road junction up to the junction of Clock House Road We have temporarily closed the southbound left-hand turn lane of Elmers End Road. Motorists will not be able to turn left from Elmers End Road onto Croydon Road during this phase Clock House Road will be temporarily closed at its junction with Croydon Road during this phase Elmers End Station Parade bus stop D remains suspended Phase Three – Elmerside Road, junction with Croydon Road Following on from phase 2, our engineers will move away from the junction of Croydon Road and Elmers End Road to begin work on Elmerside Road at its junction with Croydon Road in the right-hand turn junction for approximately two weeks To allow us to complete our work safely we need to temporarily close the right-hand turn lane of Elmerside Road at the junction of Croydon Road. Motorists will not be able to turn right from Elmerside Road onto Croydon Road Signed diversions will be in place for diverted traffic The pedestrian crossing around our work area will also be suspended