Beckenham Improvements work – 6 August 2018
Burnhill Road / Kelsey Square Junction with High Street
- The junction works are now complete. It will be reopened to traffic from Monday 6th August. All temporary traffic management and parking suspensions which have been in place since May will revert back to pre these works. A traffic marshal will be in attendance in Burnhill Road on 6th August from 0800 – 1700 to help residents and road users. Parking dispensation during the works will finish on Monday 6th August. All traffic management will revert to normal except for left turns out of Kelsey Square on to the High Street.
Bus Stop Fairfield Road and Temporary High Street Road Closure
- The temporary black top, tarmac will be removed on the 6th August for a new bus stop. The granite benches will be installed over the night of the 7th/8th.
- The High Street to Fairfield Road will be closed Tuesday 7th August from 20.00 pm to 04.00 am Wednesday 8th August. Temporary diversions will be put in place during this time. • The kerbing and paving has commenced on the North East corner of the War Memorial roundabout.
- Forthcoming Works.
- Paving will be completed in part of Burnhill Road.
- War Memorial Roundabout • Paving works will continue on the North-East corner of the War Memorial roundabout outside the cinema. This is estimated to take 2 weeks. Street lights will continue to be installed at various locations. Cycle stands to be installed at various locations.
- • As from Monday 30th July snagging work has taken place on the tree planters at Beckenham Green. The resin around the seating area should be laid down on 31st August. Preparation work for this will begin two days prior to the resin laying stage.
- • Kerb laying, new drainage and paving has almost completed between Burrell Row and Village Way.