Beckenham Green
• As from Monday 30th July snagging work will be taking place on the tree planters. This work should take approximately three weeks to complete.
• The resin around the seating area should be laid down on 31st August. Preparation work for this will resume two days prior to the resin laying stage.
This section of the green will be out of bounds to the general public from Monday 30th July through to 1st September. The rest of the green will be accessible through that time.
Completed works.
The junction of Burnhill Road Junction with The High Street is now open to pedestrians.
• The paving is complete on the North West corner of the War Memorial roundabout.
• Paving between Prezzo and Zizzi has been completed.
• Kerb laying and new drainage has been completed between Burrell Row and Sainsbury. Paving has commenced.
Phase 5 works Lidl to Village Way.
• The junction between Burnhill Road and Kelsey Square will be reopen the week starting Monday the 6th August and all traffic management will revert to normal except for left turns out of Kelsey Square on to the High Street.
• Paving will be laid in part of Burnhill Road.
War Memorial Roundabout
• Groundworks will continue on the North-East corner of the War Memorial
Roundabout outside the cinema.
• Street lights will continue to be installed at various locations. Cycle stands to be installed at various locations.