Beckenham High Street Improvements Update

Beckenham Improvements work update – 2 July 2018

Completed works.

  • The kerbing and paving has commenced on the North West corner of the War Memorial roundabout.
  • Paving has continued outside Prezzo and across the Kelsey Square / High Street junction and kerbing and has continued outside Haks barbers.
  • Between the War Memorial roundabout and Burrell Row the paving and kerbing has almost been completed.

Phase 5 works Lidl to Village Way.

  • From Monday the 21st June the junction between Burnhill Road, Kelsey Square and the High Street has been closed to traffic. Kelsey Lane remains two-way between Uplands and Wayside where it is closed to traffic. Pedestrian access is maintained from Burnhill Road, Kelsey Square and Kelsey Lane to the High Street. From Fairfield Road to Kelsey Park Road the one way has been reversed so traffic drives up Fairfield and left into Burnhill Road.
  • Preparation and laying of paving will continue at Kelsey Square. The construction works will continue in the second part of the carriageway.
  • The parking bays outside Zizzi will be retained for deliveries only.
  • The footway between Burnhill Road and the High Street has been reinstated but is currently narrowed for safety reasons. It is therefore very difficult for wheelchairs and pushovers to navigate. We apologise for this and will try to open it to its full width ASAP.

Phase 6 War Memorial roundabout to Burrell Row

  • Paving is due to be completed

War Memorial Roundabout

  • Paving work will continue on the third corner of the War Memorial roundabout.
  • Street lights are being installed at various locations.
  • Two way traffic has been reinstated between Bromley Road and Manor Road.
  • Two way traffic has also been reinstated between Thorntons Corner and Fairfield Road to enable access to Fairfield Road without using the main diversion.