Beckenham Improvements work update – 18th June 2018
Completed works.
- Substantial kerbing and paving has been laid on the South-West corner of the War Memorial roundabout.
- Paving has continued outside Prezzo and across the Kelsey Square / High Street junction and kerbing has been continued outside Haks barbers.
- Electrical connections are completed for the pedestrian crossing opposite HSBC.
- Works on Beckenham Green have continued.
- Snagging and replacement of chipped kerbs has commenced.
Phase 5 works Lidl to Village Way.
- Preparation and laying of paving will continue at Kelsey Square.
- The parking bays outside Zizzi will be retained for deliveries only.
Phase 6 War Memorial roundabout to Burrell Road
- Excavation and kerb laying will continue.
War Memorial Roundabout
- Paving work will continue on the South-West corner of the War Memorial roundabout.
Beckenham Green
- Works to the High Street entrance adjoining St Georges Church will be completed.
Scheme Programme
The main High Street improvements are on schedule to be completed in September with only snagging of small defects and some design details to be installed after this date