Beckenham High Street Improvement works

Update – Monday 28th May 2018

  • Paving has been completed between 161 and 165 High Street.
  • Kerbing and new paving has been in laid in front of HSBC.
  • Kerbing and paving work has commenced outside the Bricklayers Arms on the South-East corner of the War Memorial roundabout.
  • New bollards have been installed at Beckenham Green.

Phase 5 works Lidl to Village Way.

  • Since Monday 21 May the junction between Burnhill Road and Kelsey Square has been closed to traffic. This will last for up to 8 weeks. Kelsey Lane remains two-way between Uplands and Wayside where it is closed to traffic. Pedestrian access is maintained from Burnhill Road, Kelsey Square and Kelsey Lane to the High Street. This set up will be monitored to see if additional signage will be required. From Fairfield Road to Kelsey Park Road the one way will be reversed meaning traffic will drive up Fairfield then turn LEFT into Burnhill Road. Lidl’s delivery lorries will use the car park, so watch out for reversing trucks. Marshalls should be directing traffic.
  • Electrical connections and reinstatement will be continued for the crossing at HSBC.
  • The laying of specially designed paving will continue outside of Prezzo.

War Memorial Roundabout

  • Paving work will continue outside the Bricklayers Arms on the South-East corner of the War Memorial roundabout.

Traffic Management

Two way traffic has been reinstated between Bromley Road and Manor Road. Two way traffic has also been reinstated between Thornton’s Corner and Fairfield Road to enable access to Fairfield Road without using the main diversion.

All diverted bus routes should return to normal when the road closures end, expected to be in late September 2018.