21st May 2018
Completed works.
- Paving has been laid between 161 and 165 High Street.
- Kerbing and new paving has been in laid in front of Lidl.
- The construction of parking bays has been completed outside 161 to 165 High Street.
- Kerbing work has commenced outside the Bricklayers Arms near the War Memorial. .
- New bollards and sub surfacing will be installed at Beckenham Green.
Next week’s works.
- From Monday the 21st the junction between Burnhill Road and Kelsey Square will be closed to traffic. Kelsey Lane will remain two-way between Uplands and Wayside where it will be closed to traffic. Pedestrian access will be maintained from Burnhill Road, Kelsey Square and Kelsey Lane to the High Street. From Fairfield Road to Kelsey Park Road the one way will be reversed meaning traffic will drive up Fairfield then turn LEFT into Burnhill Road. Lidl’s delivery lorries will use the car park, so watch out for reversing trucks. Marshalls should be directing traffic.
- Electrical connections and reinstatement will be made for the pedestrian crossing opposite HSBC.
- The laying of specially designed paving will start outside of Prezzo.
- Paving will continue between the Q-Bar and Village Way. This will require pedestrians temporarily diverted on to the new parking bays.
- Paving work will continue outside the Bricklayers Arms on the South-East corner of the War Memorial roundabout.
Two way traffic has been reinstated between Bromley Road and Manor Road. After the May Bank Holiday the High Street between Thornton’s Corner and Fairfield Road will be reopened for two way traffic to enable access to Fairfield Road without using the main diversion.