Beckenham Improvements work update 14 May 2018
Phase 5 works Lidl to Village Way.
Completed works.
- The road resurfacing has been completed to Lidl, and the suspended parking bays reopened.
- Kerbing and new paving has been in laid in front of Lidl.
- The construction of parking bays has commenced outside 161 to 165 High Street.
- Kerbing work has commenced outside the Bricklayers Arms on the South-East corner of the War Memorial roundabout
Next week’s works.
- Kerbing and paving will continue from Lidl towards Prezzo (148-151).
- In Kelsey Lane a temporary, small overtaking space will be installed. In lieu of potential access disruption to residents of the road, potholes in the unmade surfacing will be filled.
- Construction of the parking bays outside 161 to 165 will continue.
- Kerbing, drainage and paving will be continued on the South-East corner of the War Memorial roundabout.
- New bollards and sub surfacing will be installed at Beckenham Green.
From the 21st May the junction of Burnhill Road and Kelsey Square will be closed to traffic (i.e. no vehicle access to the High Street).
Hours of Operation In order to maintain access to all shop entrances pavement laying will have to be conducted out of normal hours between 18pm and 20pm on some days. We do understand that this can be a nuisance and FM Conway will endeavour to keep noise disturbance to a minimum during these times.