Beckenham Improvements work update 16 April 2018
Diversion of 352 Bus from 16 April
From the 16th April the High Street from Kelsey Square to the War Memorial will no longer be two way. This is to create sufficient safe space for the contractors to carry out works on the opposite side of the road. The 352 bus will therefore have to be diverted up the High Street and around Rectory Road. Unfortunately this is unavoidable.
Phase 4 works 116 to 180 High Street.
Completed works
- Paving has been completed to 162 High Street. Kerbing has continued south of the existing pedestrian crossing.
Next week’s works.
- Footway and kerbing will continue south to The Drive. This phase of works is anticipated to be complete by the 30th April 2018 subject to construction complications or adverse weather.
- Tactile paving is being continued to be re-laid at Thornton’s Corner. A high quality granite product has always been specified for this area to complement the granite paving. The concrete tactile paving was a temporary measure.
- The entrance to Leather Alley is due to be re-laid on Thursday and Friday the 12th and 13th April. Vehicle users of the alley have been notified. Please note there is a void under the entrance, and the full extent of the problem needs to be determined. Essential works may mean works won’t be complete by the 13th April.
- The pedestrian island in The Drive will be removed in anticipation of works to this corner.
- The existing small, on street compound will be moved to the parking bays outside 258 to 262 High Street. The bays will therefore obviously be out of operation.
Hours of Operation
In order to maintain access to all shop entrances pavement laying will have to be conducted out of normal hours between 18pm and 20pm on some days. We do understand that this can be a nuisance and FM Conway will endeavour to keep noise disturbance to a minimum during these times.
Work by other contractors in Beckenham
Contractors not connected with the project have been working outside Card Factory and the side alley. Thames Water will be on site 3/4/18 to 6/04/18 to connect the new water to the flats above The Card Factory. UKPN have some extra work to complete in the alleyway between Miso and the Card Factory. The reinstatement of the paving outside The Card Factory will be completed by FM Conway.