Completed works
- Paving and kerbing has continued towards Leather Alley. There is a temporary stop at Bus Stop J near the junction of Fairfield Road and the High Street until bespoke materials are installed.
Next week’s works.
- Footway work will be continued between Specsavers to the Lidl pedestrian crossing traffic lights.
Hours of Operation
- In order to maintain access to all shop entrances pavement laying will have to be conducted out of normal hours between 18.00 and 20.00 on some days. We do understand that this can be a nuisance and FM Conway will endeavour to keep noise disturbance to a minimum during these times.
- During the Easter weekend FM Conway’s contractors will be working on the Friday and Saturday but not Easter Sunday or Monday.
Work by other contractors in Beckenham
- Contractors not connected with the project have been working outside Card Factory and the side alley. Thames Water will be on site 3/4/18 to 6/04/18 to connect the new water to the flats above The Card Factory.
- UKPN have some extra work to complete in the alleyway between Miso and the Card Factory. The reinstatement of the paving outside The Card Factory will be completed by FM Conway.