Beckenham Improvements work update 12th February 2018
Completed and soon to be completed works:
- Between the Yee Olde George Inn and Lidl, paving is complete and most of the parking bays have been reopened. Final drainage work will be completed.
- Between Thornton’s Corner and 116 High Street the considerable drainage, paving and parking bays have been completed. The parking bays have been reopened.
Phase 4 works 116 to 132 High Street.
Works commencing week beginning the 12th February 2018
- Excavation work to lay new kerbs and paving. In addition this section of work will require substantial new drainage due to the history of flooding in the area and the construction of an improved bus stop with a shelter and passenger waiting space. (At present the current bus stop comprises a bus stop sign only; with passenger waiting space restricted to a narrow footpath without seating)
- . Excavation works for the above will continue up to 164 High Street (Nero’s).
During the works the bus stop will be temporarily relocated. Transport for London will be advising the Council on their preferred location.