Beckenham High Street Improvements Update

 Work for week commencing the 2nd October 2017.

Phase 3 works:

  • Granite paving will continue to be laid at Thornton’s Corner.
  • Kerbing, drainage and paving will be installed outside the Village Garage and continue west up the High Street.
  • A materials compound will be located further up the High Street.
  • The construction of the new planters on Beckenham Green will continue. Filling the planters will commence.

Late Working

  • For the next 2-3 weeks the contractors will be working to 8pm to ensure the improvements are ready for new traffic signals to be installed.

Completed Works

  • Granite paving, kerbing and parking spaces have been installed in front of the toilets and Kelsey House.