Work for week commencing the 2nd October 2017.
Phase 3 works:
- Granite paving will continue to be laid at Thornton’s Corner.
- Kerbing, drainage and paving will be installed outside the Village Garage and continue west up the High Street.
- A materials compound will be located further up the High Street.
- The construction of the new planters on Beckenham Green will continue. Filling the planters will commence.
Late Working
- For the next 2-3 weeks the contractors will be working to 8pm to ensure the improvements are ready for new traffic signals to be installed.
Completed Works
- Granite paving, kerbing and parking spaces have been installed in front of the toilets and Kelsey House.