Work for week commencing 11 September 2017.
Phase 3 works:
- In front of Kelsey house and the former toilets works will continue to excavate the highway, install additional drainage and the new introduction of new kerbing will continue.
- The temporary asphalt surfacing on the north-west corner of Thornton’s Corner is being excavated for the laying of the granite paving.
- Thames Water has had a problem with one of their water mains. At present they are still investigating the problem. As a consequence surfacing work in the section of The High Street between Thornton’s Corner and Beckenham Junction has been temporarily stopped.
- The construction of the new planters on Beckenham Green will continue.