Beckenham High Street Improvement Updates

Work for weeks commencing the 26th June 2017. Provided by Conways.

  • Kerb laying and new paving will commence north from Pierluigis towards Church Avenue. Car parking will be suspended at this location.
  • Strengthening materials will continue to be laid under the new parking bays along The High Street between Rokewood Apartments and Thornton’s Corner.
  • Additional drainage will continue to be installed at Thorntons Corner and new kerbing will be completed.
  • Temporary surfacing will be laid at Thorntons Corner to reopen the pavement and remove the safety barriers.
  • The construction of the new planters on Beckenham Green will continue.

Previous completed works

  • Structural works for the Beckenham Green planters has continued.
  • The crossover to Rokeswood Apartments was completed (1 day earlier than anticipated).
  • Drainage, road strengthening and kerbing has been laid at Thorntons Corner.