Beckenham Improvements work update – supplied by Conways
Work for weeks commencing the 5th June 2017.
· Foundation are continued to be laid for the planters on Beckenham Green. The structures have been designed in consultation with the Councils Arboriculturalist. Each root will be boxed in a pipe/chamber to protect it with leverage for growth.
· Preparation works for new kerb alignment between 106 High Street and 62 High Street will continue with trial holes on Thornton’s Corner, to confirm the location of underground services.
· It is anticipated that Transport for London will carry out modification works to the traffic signals on the corner of Albemarle Road and the High Street.
Previous completed works
· Kerbing and paving on Bromley Road will be completed.
· Foundations for the planters on Beckenham Green have been commenced.