Beckenham Improvements work update

Work for week commencing the 1st May, from Conways

·         Work continues on both the corners of Bromley Road junction with the High Street and outside 47-71 High Street. The tree trial pits outside 47-71 will be filled until planting in the autumn.

·         External contractors will remove the two trees outside 47-71 High Street, to be replaced by six trees.

Previous completed works

·         Paving and new kerbs were continued to be laid on both sides of Bromley Road.

·         Kerb realignment in front of 47 to 71 High Street almost complete.

·         Trial holes for new trees in front of 47 to 71 High Street have been dug and it has been confirmed that 6 trees can be planted.

·         Road resurfacing at the High Street / Albemarle Road / Rectory Road / Southend Road junction completed.

·         New advance notification signs have been erected on lampposts approaching the High Street.